Expandable Endwall on a Steel Kit and When to Order It
A guy in eastern Washington called me three years after I helped bolt up his 40x60 shop. He wanted another 40 feet on the back end for a second lift bay. The frames were fine, the slab had room, the county was agreeable.

A guy in eastern Washington called me three years after I helped bolt up his 40x60 shop. He wanted another 40 feet on the back end for a second lift bay. The frames were fine, the slab had room, the county was agreeable. Then we pulled the old drawings and found a bearing endwall with 6 inch cee columns on 20 foot centers, no rigid frame at the back, and the whole conversation turned into a demolition quote instead of an extension quote.
That is the thing nobody explains well when you are ticking boxes on an order form. The endwall choice on a steel building kit is not a trim detail. It decides whether your building can grow later for a few thousand dollars or whether growing means taking the back wall apart and setting a new frame. I have erected both kinds, and I have watched owners regret the decision in both directions.
What an expandable endwall actually means on the order form
A standard endwall, sometimes called a bearing frame endwall, uses light cold formed columns and rafters that carry only the wall and roof load right at that end. They are cheap, light enough for two people to stand up, and they are not designed to carry half a bay of roof. There is nothing wrong with them. Most garages and storage buildings in this country have them at both ends.
An expandable endwall replaces that light frame with a full rigid frame, identical to the interior frames. The wall panels and girts hang off it, but structurally it is a clear span frame that could carry roof load from both sides. When you extend the building later, you unbolt the panels and girts from that frame, set new frames beyond it, and the old endwall quietly becomes an interior frame.
On drawings the giveaway is the frame line callout. If the back frame on sheet E1 reads the same as frames 2 through 5, you have an expandable end. If it shows a separate detail with lighter sections and wind columns, you do not. Ask your dealer to point at it on the drawing rather than relying on the order confirmation line, which on two orders I have seen said "expandable" where the steel said otherwise.
The price gap, line by line
Here are real numbers from a 50x80 clear span job I helped put up outside Spokane last spring, 26 gauge panels, 20 psf ground snow. The owner priced both endwall options with the same manufacturer, same week.
| Item | Standard endwall | Expandable endwall |
|---|---|---|
| End frame steel | $2,850 | $7,400 |
| Anchor bolts and base plates | $180 | $640 |
| Extra concrete for two larger piers | $0 | $1,100 |
| Engineering and drawing revision | Included | $0 |
| Crane time on erection day | Included | $450 |
| Total difference | About $6,560 more for expandable | |
That gap scales roughly with width. On a 30 foot wide building it lands closer to $3,000. On a 70 foot clear span I quoted in Idaho it was north of $11,000, because the end frame rafters got deep enough to need a second pick.
Now the other side of the ledger. Extending that same 50x80 later with an expandable end costs you new frames, purlins, girts, panels and a slab pour. Extending it with a standard end costs all of that plus teardown labor, a new engineered frame to replace the bearing end, new anchor bolts drilled and epoxied into cured concrete, and panels that will not color match after three years of fade. On the Washington job that delta came to about $14,000 on a $46,000 addition.
Why "order it just in case" is bad advice
You will read on forums that the expandable endwall is cheap insurance and everybody should get one. I disagree, and I say that as the guy who gets paid to do additions.
The reason is simple arithmetic about which end grows. Buildings extend in one direction, almost always the one with open ground and no utilities in the way. Ordering both ends expandable, which some dealers will happily sell you, doubles the premium to protect an end that physically cannot grow because the septic field or the property line sits twelve feet away. I have seen that order twice. Both times the owner paid for a rigid frame he will never unbolt.
The second reason is that most people do not extend. Across the jobs I have walked since 2019, I would put the share of buildings that actually got lengthened at somewhere under one in six, and of those, more than half got a lean to instead because it was cheaper and the owner only needed covered storage. A lean to kit for a steel building does not care what kind of endwall you have, and it adds covered square footage for roughly 40 percent of what a full extension costs per square foot.
So the honest version of the advice is narrower. Order one expandable endwall, on the end that has open ground, when you have a specific reason to think you will need the length within about ten years. Business growth, a second vehicle bay you already know is coming, a tenant who wants more space. Not a vague feeling.
Retrofitting a standard endwall later
It is doable. I have done it four times. What it looks like in practice: you strip the end panels and girts, shore the roof purlins at the second frame line, cut out the bearing columns and end rafters, drill and epoxy new anchors into the existing slab edge or pour a new pier, then set the rigid frame. Figure four to six days with a crew of three plus a telehandler.
Two things bite people here. The first is slab edge thickness. Most slabs get a thickened edge under a bearing endwall that is sized for a bearing endwall, often 12 inches where a rigid frame column needs a pier 24 to 36 inches deep. That means saw cutting and a new pour, and you cannot know until someone digs or shoots it with a cover meter. The second is that the original design may not have included the moment loads at that frame line, so a licensed engineer has to look at the whole building, not just the new frame. That letter runs $800 to $2,200 in my experience.
Before you order either way, count what actually ships so you know which end frame you are getting. Our walkthrough of steel building kit delivery and how to inventory every part covers reading part marks against the bill of materials, which is where you catch a mislabeled end frame while the truck is still there.
How to decide before the drawings go out
Stand at the back of your pad with the site plan. Measure to the property line, the septic, the well, the power drop, the turnaround you need for a truck. Write the number down. If you do not have at least the building width plus 25 feet of clear usable ground on one end, the expandable premium buys you nothing, because you could not extend there even with the right frame.
If you do have the room, ask your dealer for the two quotes separately rather than as an upgrade line. The upgrade framing hides the fact that you are also buying extra concrete and crane time. And ask the question I now ask on every order: does the slab detail change, and by how much. On the Spokane job that was the $1,100 nobody had mentioned.
One more thing worth doing this week if you are still at the quoting stage. Read through what comes in a metal building kit and what does not and then write your dealer a short email asking him to confirm in writing which frame line is expandable and what section size it uses. A dealer who answers that cleanly is a dealer who read your drawings.
FAQ
How much more does an expandable endwall cost?
On buildings 30 to 50 feet wide, usually $3,000 to $7,000 more than a standard bearing endwall once you include the deeper piers and the extra crane pick. Wider clear spans cost more because the end frame rafters get heavier.
Can you extend a steel building that has a standard endwall?
Yes, but you replace that end frame with a rigid frame first, which usually adds $10,000 to $16,000 to the addition. Budget for a new pier, an engineer's letter and panels that will not match the faded originals.
Should both ends be expandable?
Rarely. Only if you genuinely have open ground and a plausible use on both ends. Most sites only grow one direction, and paying twice to keep both options open is money that would do more good in heavier gauge panels or better insulation.
Does an expandable endwall change the permit?
Not the permit itself, since you are permitting the building as built. It does change the stamped drawings and the foundation plan, so make sure the set you submit matches the steel you ordered rather than an earlier revision.
More in Building Kits
Building Kits
Steel Building Kit Dealer or Manufacturer Direct
A man outside Bozeman sent me his kit paperwork last February because his 40x60 shop was lying on the slab in pieces and nobody...
Building Kits
Buying a Used Steel Building Kit and What to Check First
A used steel building kit listed at half the new price looks like the easiest money you will ever save, right up until the...
Building Kits
Lean-To Kit for a Steel Building and What to Order
You have a steel building on order or already standing, and the tractor, the boat trailer or the firewood still has nowhere dry...